Installation Preparation

Before you get started make sure you have the following:

  • Project’s Wiring diagram - Provided by Galooli Support

  • CE Transducer CE42 Meter

  • The power source of +12V DC to power the Galooli RTU (Elara)

  • Electrical wires

  • Electronic tools – screwdriver, Multimeter, & f-crimp tool

 Additional information:

  • The device is designed to be installed on a din rail

  • Make sure that you have sufficient space for its mounting

  • We recommend mounting the AC meter next to phase breakers - this act can simplify the process of disconnecting the cables from the breakers, passing the load cables through the meter, and then connecting them back to the breakers

Configuration Preparation

  • PC or laptop computer

  • Power Center installed - Click here to download. Credential info can be received from your Account Manager or Galooli support

  • ZonMax installed - Click here to download. Credential info can be received from your Account Manager or Galooli support

  • RS485 to USB converter - Refer here for driver installation instructions.

  • Project’s Wiring diagram - Provided by Galooli Support.

Note! Make sure your computer recognizes the COM port at the “Device manager”. Otherwise, install the proper driver.