This document outlines the installation process of the Galooli solution, dividing it into three primary phases:
...
The following chart outlines the structure of the three phases described below:
...
Pre-installation
The pre-installation phase is crucial for establishing the foundation for a successful deployment of the Galooli solution. This phase has two primary objectives:
...
Estimated Installation Time by Scope
Scope | Number of Sites | Installation Time (H) | Total Time (H) | Total Time (D) |
Basic | 120 | 2 | 240 | 10 |
Medium | 500 | 3 | 1,500 | 62.5 |
Advanced | 250 | 4 | 1,000 | 41.66 |
Total | 970 |
| 2,740 | 114.2 |
Installation
The installation phase centers on the essential on-site activities required to ensure that all physical components are correctly installed and fully operational. This phase is vital for establishing the infrastructure necessary for the Galooli solution to function effectively.
Pre-Installation Checklist: This checklist must be completed by the Project Manager of the Installation Team before arriving on site to ensure that all preparations are in place.
Pre-Installation ChecklistInstallation Form: This form must be filled out by the Installation Team on site to document the installation process and confirm that all tasks have been completed.
Galooli Installation FormCheckout Report: The on-site Installation Team is responsible for completing this report to confirm the successful completion of the installation process before leaving the site.
Checkout Form (jotform.com)
Post-installation
The post-installation phase focuses on verifying the successful completion of the installation and ensuring that data from the connected assets is being transmitted seamlessly to the Galooli Cloud. This phase also involves any necessary troubleshooting and final adjustments to maintain ongoing reliability and optimal system performance. The phase concludes with the customer’s approval, confirming that data streaming and validity meet the required standards.
...
.
...
Data Accuracy Validation: A data "sanity check" must be performed within 48 hours after installation, in coordination with back-office and/or NOC personnel, to validate the integrity and accuracy of the data.
Data Validation FormCustomer Approval: The installation process is only considered complete upon receiving formal written confirmation from the customer’s Project Manager, confirming their satisfaction with the installation.
...
Below are estimated installation times per device and Site Scope:
SN | Device | Average Time (Minutes) | SCOPE 1 | SCOPE2 | SCOPE 3 |
1 | Gateway | 20 | 20 | 20 | 20 |
2 | Rectifier SNMP Integration | 30 | 30 | 30 | 30 |
3 | Battery BMS Integration | 30 | 30 | 30 | 30 |
4 | DC Meter | 20 | 20 | 20 | 20 |
5 | Grid AC Meter | 40 |
| 40 | 40 |
6 | AC Tenant Meter | 40 |
| 40 | 40 |
7 | Temperature Sensor | 25 |
| 25 | 25 |
8 | Door Sensor | 25 |
| 25 | 25 |
9 | Smoke Sensor | 25 |
| 25 | 25 |
10 | Generator Panel Integration | 20 |
|
| 20 |
11 | Ignition Relay installation | 20 |
|
| 20 |
12 | Fuel sensor Installation | 55 |
|
| 55 |
13 | Checkout | 30 | 30 | 30 | 30 |
14 | DB/Tray | 20 | 20 | 20 | 20 |
|
| 400 (6.7 Hrs.) | 150 ( 3 Hrs.) | 305 (5Hrs) | 400 (7 Hrs.) |
Team Members
The following table outlines the estimated number of back-office staff and technicians required for new installations and ongoing maintenance. These figures are based on assumptions for an average project and are subject to change depending on project-specific conditions and evolving circumstances.
TASK | BACK-OFFICE STAFF | TECHNICIANS |
New installation | 1 | 5 |
Ongoing Maintenance | 1 | 7 |
Training
To advance the installation process, Galooli must collaborate with the customer and/or partner to develop a comprehensive Installation, Configuration, and Software training program. The key components of this program are as follows:
...
Scope | Duration (Hours) | Duration (Days) |
1 | 4-5 | 1 |
2 | 8-11 | 1.5 |
3 | 10-13 | 2 |
Software Overview | 2-3 | 1 |
Materials
Gateway
Ultra gateway
A/C Monitoring - A/C Current Sensor
Door, Temperature & Smoke Sensor
...
# | ITEM DESCRIPTION | Unit ( Pc/Mtr/Set of) | Comments |
1 | Draw tape | Per roll of 50M | Fitted with a flexible head and draw eye for minimal resistance whilst navigating cable through conduit with multiple bends |
2 | Foldable ladder 2.5 m | pc | 2.6m height, Aluminum Alloy |
3 | Allen Keys Set | Set of 9pcs 1.5mm-10mm | 2, 2.5, 3, 4, 5, 6, 8, 10mm(each for 1 PCS) Material: CR-V |
4 | Cable Stripper | pc | LY25-1: Wire diameter: 4-28MM |
5 | Pliers | pc | Specification:7“, Length:203mm, Maximum shearing ability: iron wireφ3.0, copper wireφ3.5 |
6 | Screw Drivers Set | Set of 6pcs (3 Star and 3 Flat) | 8 PCS G series screwdriver set |
7 | 600A DC/AC Clamp meter | pc |
|
8 | Side cutter - Small size | pc | max opening: 14mm, length: 119mm, weight: 0.19kg |
9 | Wire Stripper/Cutter 16-26 AWG | pc | for cutting wire, 30mm max, stripping wire 0.2-1.25mm² |
10 | Rechargeable BOSCH Mini Portable Drill + Batteries | pc | Mini Portable Electric Drill for driving screws and nuts |
11 | Hand Lugging tool | pc |
|
12 | Mobile smart phone | pc |
|
13 | Laptop | pc |
|
14 | Laptop bag | pc |
|
15 | SD Card Reader USB | pc |
|
16 | RS485 to USB Converter | pc |
|
17 | HDMI Cable | pc |
|
Consumables
# | Item | UOM | Qty per site | Specifications | Remarks |
1 | Cable lugs SC4-4 | Pcs | 4 | SC4-4/Screw hole: M4 | Included in Installation KIT |
2 | End Cables Pack - Red | Pcs | 4 | Wiring range: 1.0mm² Tube Length: 10mm | Included in Installation KIT |
3 | End Cables Pack - Black | Pcs | 4 | Wiring range: 1.0mm² Tube Length: 10mm | Included in Installation KIT |
4 | End Cables Pack - Orange | Pcs | 4 | Wiring range: 1.0mm² Tube Length: 10mm | Included in Installation KIT |
5 | End Cables Pack - Blue | Pcs | 4 | Wiring range: 1.0mm² Tube Length: 10mm | Included in Installation KIT |
6 | Cable ties White - 3.6*300 | Pcs | 10 | 3.6mm x 300mm; white color | Included in Installation KIT |
7 | Insulating tape | Pcs | 1 | PVC electrical insulation tape black color, 10M per roll | Included in Installation KIT |
8 | Flexible conduit White 3/4 | Mtrs | 10 | internal diameter 23mm;/external diameter 28.5mm | Included in Installation KIT |
9 | 2 Meter Ethernet Cable | Pcs | 1 | CAT6e/ 2m | Included in Installation KIT |
10 | 12 Meter Ethernet Cable | Mtrs | 1 | CAT6e/ 12m | Included in Installation KIT |
11 | 4 Core Cable | Mtrs | 10 | 4 Core Cable (4 X 1.0 mm²) | Included in Installation KIT |
12 | 2 Core Cable | Mtrs | 10 | 2 Core Cable (2 X 1.0 mm²) | Included in Installation KIT |
13 | Earth Cable Yellow Green | Mtrs | 4 | 4mm | Included in Installation KIT |
14 | Blind Rivets Small | Pcs | 5 | 1/8 inch x 1/2 inch | Included in Installation KIT |
15 | Self Tapping Screws | Pcs | 5 | 8mm*1.5 inch | Included in Installation KIT |
16 | Drill Bits 4mm | Pcs | 1 |
| Included in Installation KIT |
...