ZonMax Layout Configuration
After you finished If you have completed wiring and configuring the device, we can move on to the device’s configuration on the ZonMax platform.
Open ZonMax using your credentials.
...
2. Select the relevant unit you wish to configure.
...
3. Navigate to “Live Display” and check the “Config” radio button.
...
4. Go to the “Global” section and check “Grid voltage phases 1, 2, and 3” under the global section.
...
5. If a relay is connected to the generator then go to the “Generators” section and check the “DG 1\2 running”.
...
6. Click “Save”.
ZonMax IO Configuration
Double-click the relevant unit and navigate to the “IO’s” tab.
...
2. Double-click on “Click to Add” for whichever type of input you want.
...
Input Name
...
Input Type
...
Description
...
AC_Meter_Grid_Total_KWH
...
Analog
...
Power coming from X phase
...
AC_Meter_Grid.V.L[X]
...
Analog
...
Voltage value for phase - X
...
AC_Meter_Grid.I. L[X]
...
Analog
...
Current for phase X
...
AC_Meter_Grid. Disconnected
...
Digital
...
If communication exists or not
...
Input Name
...
Input Type
...
Description
...
AC_Meter_Generator_[X]_Total_KWH
...
Analog
...
Power coming from X phases
...
AC_Meter_Generator.V.L[X]
...
Analog
...
Voltage value for phase - X
...
AC_Meter_Generator.I. L[X]
...
Analog
...
Current for phase X
...
AC_Meter_Generator. Disconnected
...
Digital
...
If communications exists or not
...
Input Name
...
Input Type
...
Description
...
Colo_Meter[X].Total_KWH
...
Analog
...
Power coming from X phases
...
Colo_Meter[X]. V.L[Y]
...
Analog
...
Voltage value for phase - X
...
Colo_Meter[X].I. L[Y]
...
Analog
...
Current for phase X
...
Colo_Meter[X]. Disconnected
...
Digital
...
battery cell monitoring in Power Center, all you need to do is select the relevant layout and all the battery information will appear in the Live Display menu.
The relevant layout provided by Galooli should be selected in ZonMax
2. תמונה והסבר על מה שרואים בLIVE