Field Name

Field Meaning and Logic



Engine Hours Tampering

The digital field becomes "True" when the difference in engine hours exceeds the difference in records by more than two hours.
[2 < (ABS(engine hours difference - time difference]. The unit will display an alert if such a situation occurs.

  • The alert will be applied only to units with a generator panel installed (not applicable to units without a generator panel).

Load Power

This is the direct reading of the power value from the generator panel, or a calculation based on the voltage, current and PF read from the generator panel.


Gen PF 1-3 (Power Factor)

The Power Factor (PF) reading from the generator panel. The Power Factor will be filled with a default value of 0.95 if there is no power factor for the phase and no direct reading of power, voltage, and current (all three).