Connecting the AC meter to the Elara Terminal Block

  1. Connect the RS-485 cables from the AC meter to the Terminal Blocks of the Elara tray.

...

 The terminal number on the AC

...

 The terminal number on the AC

...

Description

...

Functionality

...

7

...

DC +12V power input

...

Powering Meter

...

8

...

DC GND

...

Powering Meter

...

15

...

Elara’s terminal block Orange data port

...

B data port

...

16

...

Elara’s terminal blocks the Blue data port

...

A data port

Image Removed

...

  1. Connect to the Elara gateway serially or over the air trough the Power Center.
    https://galooli.atlassian.net/wiki/spaces/KP/pages/2643558401/Elara+Installation+and+Configuration#APN-%26-Cloud-Server-Configuration

  2. Connect the Elara to the battery hub directly via ETH or via switch (if necessary)

...