The Request
An organization that manages off grid hybrid telecom sites is interested in developing a report that will demonstrate how to optimize hybrid site performance and reduce generator run time.
This is the request of the company:
...
Use the "Detailed Graph" view in order to gain a full understanding of the site's operational status .
תמונהand in order to determine why the batteries are only working for a short period of time.
As you can see in the graph below, despite the fact that the batteries were charged, they were not used even though they were supposed to be. It is likely that this was due to a fault in the configuration of the site which failed to utilize batteries in the required time even though the site is hybrid. At some point the batteries began to breakdown as they should have.
...