The Schneider Electric iEM3255 AC Energy Meter is a compact, DIN-rail mounted device for monitoring energy consumption in single-phase or three-phase systems. It provides accurate measurements of energy, voltage, current, power factor, and frequency.

Info

Whenever the meter is connected to a CT ring, the ring must be configured within the meter. Detailed information about the process can be found in this article.

Image Modified
Table of Contents
minLevel1
maxLevel6
outlinefalse
stylenone
typelist
printabletrue

Supported Models

Communication Methods

iEM3255

RS485

Network configuration for RS485 connection

...

Device Baudrate

...

 19200

...

RS485 Wiring diagram

TBA

Manufacturer User Manual & Instructions

View file
nameוEM32 User Manual.pdf

View file
nameוEM32 Instruction Sheet.pdf

Network Configuration for RS485 connection

Device Baudrate

 19200

Supported CT Rings

Installation and Configuration

  1. Connect the power cables to the AC meter V1 and Vn (neutral). Do not connect the cables to a power source at this time.

    image-20241015-114657.pngImage Added

  1. Connect the current cable between the AC meter ands the CT rings.

image-20241015-114956.pngImage Added
  1. Phase Lines Installation

Safety: 

  • Before installing the load cables and connecting the voltage lines, it is necessary to cut off the AC power. Once the wiring procedure is completed, you may turn the AC power back on

  • Any electrical installment should be carried out only by a certified high-voltage electrician

The AC power cable should be threaded through the ring as shown in the picture below.

image-20241015-115430.pngImage Added
  1. The AC meter should be connected to a power source and the display should be turned on.

image-20241015-115719.pngImage Added

5. In order to start the AC Meter configuration please simultaneously press the "OK" and "ESC" buttons for five consecutive seconds until you see the word "Password" on the screen of the AC meter.

image-20241015-121559.pngImage Added


6. The password is 10. To edit the digits, use the "OK" button to move between them and the "Arrow" button to change them. When you have entered the password, click "OK" three times to complete the process.

image-20241015-121759.pngImage Added
  1. Click the "OK" button until you reach the "CT & VT Ration". To access the menu, click "OK". Verify that the "CT Secondary" appears as it does in the CT ring you use, click "OK", and then verify that the "CT Primary" appears as it does in the CT ring. To complete this step, click on “OK ”.

image-20241015-122935.pngImage Added



image-20241015-123246.pngImage Added
image-20241015-123036.pngImage Addedimage-20241015-123149.pngImage Added
  1. You can then set the time and

...

  1. date and complete the process by clicking "OK" until it is complete.

  2. To connect the AC meter to the Galooli Gateway (RS485), you will need to connect two cables, one to the "D1/+" and the other to the "D0/-".

AC Meter

Galooli Gateway

D1/+

A

D0/-

B

image-20241015-124300.pngImage Added

Power Center Configuration

image-20241015-125009.pngImage Added