Lesson Highlights

Name of the lesson

...

  • Prior to arriving on site, review the bill of materials (BOM) list and ensure you have all the necessary equipment and hardware. The technical booklet provides detailed information about the hardware that should be installed.

  • Installation Form - It is very important to use the installation form (prepared in advance by Galooli) before and during installation. Upon arrival at the site, the form must be opened immediately.
    Installation Form - Template

...

Configuration Process

The configuration process of a new gateway in an organization is a crucial step in receiving proper data from the gateway and obtaining the maximum amount of accurate data from the Galooli solution.

...

Step 2 - Basic ConfigurationTBA

Different gateways require different configuration processes, but the process of adding sensors to the gateway is the same.

Please refer to the following link for various configuration documents - Stationary Asset Gateways

Galooli Solution Basic Configuration

...

Before leaving the site and completing the installation, the checkout form is intended to ensure that the installation process has been completed correctly. There is a test process included in the form that includes the installation and configuration of the hardware. In order to complete the form, the installer and the back office of the organization must work together.
https://galooli.atlassian.net/wiki/spaces/KP/pages/2554986506/Online+Pre-Made+Forms+Store#Checkout-Form

Technician

  • Finish complete installation as per technical booklet

  • Configure all devices in Power Center platform

  • Fuel accuracy test done (if relevant)

  • Installation and QA report completed and submitted

...

  • Installation and QA report review

  • Configuration checks - מזה?

  • Alarm test

  • Jotform checkout report completed

...